A concrete cylinder is tested at 7 days and reaches 2,100 psi against a specified 28-day strength of 3,000 psi. What is the correct conclusion?
- The mix has failed and must be rejected
- The result is consistent with normal strength gain and the 28-day test governs
- The cylinder was cured incorrectly
- The strength must be extrapolated linearly
A subcontractor has not been paid and wants to preserve lien rights. What is generally the first requirement?
- Filing suit within one year
- Serving a preliminary notice within a statutory period after first furnishing
- Recording the lien before starting work
- Notifying the surety
Which of the following best describes a change order?
- A verbal instruction from the owner
- A written modification to the contract covering scope, price and time
- A request for information
- A supplement to the schedule of values
Under OSHA fall protection rules for construction, at what height does the general trigger apply?
- 4 feet
- 6 feet
- 10 feet
- 15 feet
Weighting. Free question banks tend to cluster around whatever is easy to write, which is usually safety numbers. The published blueprint gives Procurement and Contracting 31 of 125 questions, and almost no free set reflects that.
Use them for the index
The right way to work a free set is with the books open, tabbing where you land. Then even a badly weighted question set builds something useful.
Scoring them closed book tells you very little, since the real exam is open book.
Common questions
Are free NASCLA practice questions worth using?
Yes for format and for building your index, less so as a score predictor since most sets do not match the published weighting.
What is the OSHA construction fall protection trigger?
Six feet above a lower level. Four feet is the general industry figure and the common wrong answer.
When is concrete strength measured?
At 28 days. A 7-day break is an early indicator, not an acceptance decision.
What does a change order cover?
Scope, price and time, in writing.
How should I work free questions?