Practice questions: site construction
Site Construction is 15 of 115 scored questions. These four cover the protective system trigger, soil classification, spoil pile setback and an earthwork volume calculation.
Fifteen questions, and the soil table answers a good proportion of them.
A trench is 4 feet 8 inches deep in Type B soil. Is a protective system required?
- Yes, any trench requires one
- No, the trigger is 5 feet
- Yes, because it is Type B soil
- Only if employees will enter it
Soil at a site was excavated and backfilled two years ago and is now being reopened. How is it classified?
- By testing, as any other soil
- Type A if it tests at 1.5 tons per square foot
- Type C, because it has been previously disturbed
- Type B, as a default for backfill
How far back from the edge of an excavation must spoil be placed?
- At least 2 feet
- At least 4 feet
- At least 6 feet
- Any distance, if sloped
A slab measures 30 feet by 40 feet at 4 inches thick. How many cubic yards of concrete, before waste?
- About 14.8
- About 400
- About 44.4
- About 4.4
Two tables and one conversion
The soil table, the depth triggers, and 27 cubic feet to a cubic yard. Between them they cover most of this category.
Common questions
When is a protective system required?
At 5 feet deep, unless the excavation is entirely in stable rock.
How is previously disturbed soil classified?
Type C, regardless of what it would otherwise test at.
How far back must spoil be placed?
At least 2 feet from the edge.
How do I calculate concrete volume?
Length times width times thickness in feet, then divide by 27 for cubic yards.
What covers most of this category?
The soil classification table, the depth triggers, and the cubic feet to cubic yards conversion.