Crane and Rigging Safety: CHST Exam
Crane questions test the full lift: equipment setup, rated capacity, ground support, rigging inspection, sling geometry, communication and worker exposure.
- Check the actual configuration and manufacturer ratings.
- Sling tension increases as angle from horizontal decreases, and employees must stay out of suspended-load fall zones except under limited controlled conditions.
On this page12 sections
- Plan the lift as a system
- Use the correct load chart
- Ground conditions and setup
- Inspect rigging before use
- Understand sling angles
- Hitches and load control
- Signals and qualified riggers
- Keep workers clear of suspended loads
- Power lines and surrounding work
- A worked sling example
- Stop conditions and exam traps
- A practical lift-control sequence
- Inspection
- Rigging inspected before use on each shift and as needed during use
- Capacity
- Use actual crane chart configuration, radius, load and component ratings
- Sling geometry
- Lower angle from horizontal increases leg tension
- Fall zone
- Keep employees out except under specified limited conditions
Plan the lift as a system
Identify the load, crane configuration, operating radius, ground support, travel path, nearby workers, weather and communication method. A load chart applies to its stated configuration. The machine’s headline capacity is not available at every boom setup or radius. A qualified lift plan uses the actual crane, load and site conditions.
Assign who calculates the load, inspects rigging, directs the lift, signals and controls access. The question may ask for immediate protection or the program weakness that caused an unsafe practice. A complete answer addresses both the exposure and the system around it.
Use the correct load chart
Determine load weight, center of gravity, attachments and rigging weight as required for the capacity calculation. Confirm the chart for boom length, counterweight, outrigger position, operating quadrant, radius and reeving. Use manufacturer instructions. Never assume a chart value applies to a different configuration.
Capacity usually falls as radius increases. Account for where the load is picked and where it will land, since the radius can change. If the load weight, configuration or center of gravity is unknown, stop to get reliable information. Intuition is not a substitute for the chart.
Ground conditions and setup
Check for utilities, voids, backfilled soil, slopes, excavations and buried structures. Follow requirements for level, outriggers, mats and blocking. A crane near an excavation may load unstable soil. A mat spreads force only when sized and supported correctly; it does not fix unknown ground conditions by itself.
Reassess after weather or ground disturbance. Coordinate with the excavation competent person where the work is near a trench or pit. Verify buried structures before placing outriggers. If bearing support is uncertain, stop and assess rather than adding random cribbing.
Inspect rigging before use
OSHA 29 CFR 1926.251 requires rigging equipment to be inspected before use on each shift and as necessary during use. Remove defective equipment from service. Slings need legible identification and rated capacity for the hitch and configuration. The tag tells the rigger what the equipment can support.
Look for cuts, broken stitching, heat or chemical damage, deformation, cracks, wear, missing parts and defects appropriate to the sling type. Rejection criteria depend on construction and manufacturer guidance. Do not invent one universal discard threshold for wire rope, synthetic web and chain slings. Quarantine an item if its condition or rating is uncertain.
Understand sling angles
As the angle between a sling leg and horizontal becomes smaller, tension rises for the same vertical load share. A simplified symmetric calculation is T = W divided by n times sin θ, where W is load, n is equally loaded legs, and θ is the angle from horizontal. Actual lifts may not share equally, so a qualified rigger must verify the arrangement.
For example, a 2,000-pound load shared evenly by two legs at 60 degrees from horizontal gives about 1,155 pounds per leg. At 30 degrees, it gives 2,000 pounds per leg. This illustration assumes equal sharing and omits other effects. Check actual ratings and manufacturer instructions; do not apply a universal sling-angle reduction.
Hitches and load control
Vertical, basket and choker hitches load a sling differently. A basket may support a load with two legs only if its geometry and stability permit. A choker can reduce rated capacity depending on how it is formed. Use the sling identification and capacity tables. Protect synthetic slings from sharp edges and avoid hardware side loading beyond its rating.
Secure the load against slipping, shifting or crushing a sling. Keep the hook above the center of gravity when feasible. An offset center can cause tilt. Tag lines can help control rotation when appropriate, but workers must stay clear of pinch points and never wrap a line around a hand or body.
Signals and qualified riggers
OSHA requires a qualified rigger for specified work, including rigging operations when employees are in the fall zone under conditions listed in the rule. Read the exact provision rather than saying a qualified rigger is required for every lift in every circumstance. The employer selects the rigger based on demonstrated knowledge, training and experience.
Only one designated signal person should direct movement at a time except for emergency stop signals. The signal method must be understood and maintained. If the operator cannot see the signal person, use compliant communication. Stop if communication fails, signals conflict or anyone identifies a hazard. A radio cannot help if noise or dead zones prevent reliable contact.
Keep workers clear of suspended loads
OSHA 1926.1425 limits employee exposure to suspended loads. Keep employees out of the fall zone except for limited tasks and conditions allowed by the rule. Necessary work in the zone must use the required rigging and positioning controls. This is not open permission to stand below a load.
Plan the hoisting route to minimize exposure. Mark an exclusion zone, control access and communicate the route. Use tag lines where appropriate and keep workers away from swing, crush and landing zones. If a load snags, stop and reassess rather than increasing force or having a worker push from a dangerous position.
Power lines and surrounding work
Before crane work, identify power lines and apply the current clearance, deenergizing or grounding requirements. The exact clearance depends on voltage and the standard’s table. Verify the current rule for the case. A spotter does not compensate for inadequate clearance.
Survey buildings, scaffolds, traffic routes, pipes, other cranes and excavation edges. A lift path that clears one obstacle may expose a neighboring crew. Coordinate with trades and suspend the lift if conditions change. Assess setup, pick, travel, placement and teardown, not just the instant the hook takes the load.
A worked sling example
A 3,000-pound load is carried by two sling legs at 30 degrees above horizontal. Under the simplified equal-share formula, each leg sees about 3,000 pounds of tension. A sling rated for 1,600 pounds per leg would not be adequate in this configuration. It is incorrect to accept it because its rating exceeds half the load.
The example ignores hitch reductions, hardware limits, unequal sharing and dynamic effects. A real lift requires a qualified rigger to verify configuration and ratings. The exam skill is recognizing that low angles increase tension and that dividing load by the number of legs can be unsafe.
Stop conditions and exam traps
Stop when load weight or center of gravity is uncertain, the chart setup is unclear, rigging tags are unreadable, a defect is found, ground support is questionable, communication fails or an exclusion zone cannot be maintained. Stop when wind or visibility makes control unreliable. Schedule pressure does not justify lifting.
Common traps include assuming capacity is constant, dividing load equally among legs without angle effects, choosing a sling without checking its identification, and assuming nobody may ever enter a fall zone. The last statement is too absolute; limited exceptions exist. Read for the exact stage: planning, inspection, hoisting, travel, receiving or emergency stop.
A practical lift-control sequence
Before lifting, verify plan, configuration, support, load weight, path, rigging identification and capacity. Assign operator, signal person and qualified rigger as applicable. Establish communications and exclusion zones. During the lift, watch for shifting, snags, changing radius, settlement, wind and communication loss. Keep people clear except where the rule permits controlled work.
After placement, secure the load before releasing rigging. Repeated crane hazards may point to weak procurement, coordination or planning. A useful corrective action names an owner and verification step, such as a pre-lift check plus sampling later lifts. Training alone is insufficient if the work design or equipment selection creates the hazard.
As the sling angle from horizontal becomes smaller, what happens to tension in each leg supporting the same vertical load?
- It decreases
- It increases
- It remains constant
- It disappears
A worker is asked to stand directly under a suspended load to guide it. What is the best response?
- Allow it if the load is light
- Keep employees out unless a specific limited exception and required controls apply
- Allow anyone wearing a hard hat
- Proceed if the operator sees the worker
Common questions
What is the safest way to answer these questions?
Identify the actual hazard and stage of work, then apply the current standard and select a feasible control.
Should candidates memorize numbers without context?
No. Know what condition each threshold governs and check task-specific exceptions.
Where should a candidate verify a technical rule?
Use the current OSHA regulation and applicable manufacturer instructions.