How far is station 18+40 from station 6+90?
- A115 feet
- B11.5 feet, since the difference is measured in stations rather than feet
- C1,150 feet
- D2,530 feet
Mock paper #2
A full paper drawn to the blueprint. Answers and worked explanations are at the back of this file.
Single-user licence. You may print this file and write on it. You may not redistribute, resell or post it. © Sitonce 2026.
Sit this the way you will sit the real one. A mock done in pieces over three evenings measures your notes, not your recall.
| Area | Questions | Share |
|---|---|---|
| Procurement and Contracting Requirements | 31 | 27% |
| General Requirements | 25 | 22% |
| Site Construction | 15 | 13% |
| Concrete | 6 | 5% |
| Mechanical and Plumbing Systems | 6 | 5% |
| Metals | 6 | 5% |
| Finishes | 5 | 4% |
| Thermal and Moisture Protection | 5 | 4% |
| Wood | 5 | 4% |
| Doors, Windows and Glazing | 4 | 3% |
| Masonry | 4 | 3% |
| Electrical Systems | 3 | 3% |
| Total | 115 | 100% |
The pass mark is 81 correct out of 115 scored questions, which PSI publishes. Any pass-rate figure quoted for this exam is an estimate - neither NASCLA nor PSI publishes one.
Circle one letter for each question.
115 questions. 330 minutes.
How far is station 18+40 from station 6+90?
What must an owner do before calling on a performance bond?
From what event does the deadline to record a lien usually run?
The paper carries one for every question, at the back. These are the three above.
Answer: C - 1,150 feet
Because Convert each station to feet and subtract. NASCLA Guide ch. 13
1,840 - 690 = 1,150 feet.
Where the other options lead
Answer: B - Follow the bond's own conditions, including notice and declaration of default
Because Modern bonds set conditions precedent: notice to the contractor and surety, a conference where required, formal declaration of default and termination, and agreement to pay the balance of the contract price to the surety or its completion contractor. Missing a step can defeat the claim. NASCLA Guide ch. 5
Where the other options lead
Answer: C - Last furnishing of labour or material, or completion as the statute defines it
Because Statutes run the clock from the claimant's last day of work or delivery, or from completion, cessation or a recorded notice of completion. Returning to do warranty or punch work generally does not restart it, which is a trap for the unwary. NASCLA Guide ch. 8
Where the other options lead
NASCLA Commercial GB: the whole syllabus taught, the questions that test it, 5 timed mocks, and all 6 PDFs to print.