NASCLA Accredited Examination for Commercial General Building Contractors

A full paper drawn to the blueprint. Answers and worked explanations are at the back of this file.

Questions
115
Time
330minutes
Mark
70%to pass
Paper
#2of 5

Single-user licence. You may print this file and write on it. You may not redistribute, resell or post it. © Sitonce 2026.

Before you start

Sit this the way you will sit the real one. A mock done in pieces over three evenings measures your notes, not your recall.

Questions
115
Minutes
330
Per question
172s
Started at
 
  1. Set a timer for 330 minutes and do not stop it. Running over is the commonest way a prepared candidate fails, and the only place you can find that out safely is here.
  2. Mark one answer for each question on the answer sheet.
  3. Answer every question. There is no penalty for a wrong answer. A blank is a guaranteed zero and a guess is not.
  4. Flag anything you are unsure of as you go. When you mark the paper, a question you flagged and got right is worth as much of your attention as one you got wrong - you do not yet know it, you guessed it.
  5. When the timer runs out, turn to the Answers section at the back of this file. Mark the paper against the quick-reference key first, fill in the score table, and only then read the worked explanations.

What this paper covers

AreaQuestionsShare
Procurement and Contracting Requirements3127%
General Requirements2522%
Site Construction1513%
Concrete65%
Mechanical and Plumbing Systems65%
Metals65%
Finishes54%
Thermal and Moisture Protection54%
Wood54%
Doors, Windows and Glazing43%
Masonry43%
Electrical Systems33%
Total115100%

Pass mark vs pass rate

The pass mark is 81 correct out of 115 scored questions, which PSI publishes. Any pass-rate figure quoted for this exam is an estimate - neither NASCLA nor PSI publishes one.

Answer sheet - paper #2

Circle one letter for each question.

1ABCD
2ABCD
3ABCD
4ABCD
5ABCD
6ABCD
7ABCD
8ABCD
9ABCD
10ABCD
11ABCD
12ABCD
13ABCD
14ABCD
15ABCD
16ABCD
17ABCD
18ABCD
19ABCD
20ABCD
21ABCD
22ABCD
23ABCD
24ABCD
25ABCD
26ABCD
27ABCD
28ABCD
29ABCD
30ABCD
31ABCD
32ABCD
33ABCD
34ABCD
35ABCD
36ABCD
37ABCD
38ABCD
39ABCD
40ABCD
41ABCD
42ABCD
43ABCD
44ABCD
45ABCD
46ABCD
47ABCD
48ABCD
49ABCD
50ABCD
51ABCD
52ABCD
53ABCD
54ABCD
55ABCD
56ABCD
57ABCD
58ABCD
59ABCD
60ABCD
61ABCD
62ABCD
63ABCD
64ABCD
65ABCD
66ABCD
67ABCD
68ABCD
69ABCD
70ABCD
71ABCD
72ABCD
73ABCD
74ABCD
75ABCD
76ABCD
77ABCD
78ABCD
79ABCD
80ABCD
81ABCD
82ABCD
83ABCD
84ABCD
85ABCD
86ABCD
87ABCD
88ABCD
89ABCD
90ABCD
91ABCD
92ABCD
93ABCD
94ABCD
95ABCD
96ABCD
97ABCD
98ABCD
99ABCD
100ABCD
101ABCD
102ABCD
103ABCD
104ABCD
105ABCD
106ABCD
107ABCD
108ABCD
109ABCD
110ABCD
111ABCD
112ABCD
113ABCD
114ABCD
115ABCD

Paper #2

115 questions. 330 minutes.

1

How far is station 18+40 from station 6+90?

  1. A115 feet
  2. B11.5 feet, since the difference is measured in stations rather than feet
  3. C1,150 feet
  4. D2,530 feet
2

What must an owner do before calling on a performance bond?

  1. ATerminate the contract and complete the work before notifying the surety
  2. BFollow the bond's own conditions, including notice and declaration of default
  3. CObtain the contractor's written agreement that it has defaulted
  4. DExhaust the retainage held before making any claim
3

From what event does the deadline to record a lien usually run?

  1. AThe date the claimant's invoice became overdue
  2. BThe date on which the owner first took occupancy of any part of the building
  3. CLast furnishing of labour or material, or completion as the statute defines it
  4. DThe date the claimant's subcontract was executed

Worked explanations

The paper carries one for every question, at the back. These are the three above.

Q1 C Ch. 3: Site Construction

Answer: C - 1,150 feet

Because Convert each station to feet and subtract. NASCLA Guide ch. 13

1,840 - 690 = 1,150 feet.

Where the other options lead

  • A.Misplaces a decimal. 115 feet is a tenth of the correct distance.
  • B.Leaves the answer in stations. 11.5 stations is 1,150 feet, and the question asks for feet.
  • D.Adds the two stations. Distance between two points is the difference, not the sum.
Q2 B Ch. 1: Procurement and Contracting Requirements

Answer: B - Follow the bond's own conditions, including notice and declaration of default

Because Modern bonds set conditions precedent: notice to the contractor and surety, a conference where required, formal declaration of default and termination, and agreement to pay the balance of the contract price to the surety or its completion contractor. Missing a step can defeat the claim. NASCLA Guide ch. 5

Where the other options lead

  • A.Completes first. Completing before involving the surety removes its options and prejudices its position, which is a common defence.
  • C.Requires the contractor's agreement. A defaulting contractor rarely agrees, and the bond does not require it.
  • D.Exhausts retainage first. Retainage is applied to the cost of completion but is not a precondition.
Q3 C Ch. 1: Procurement and Contracting Requirements

Answer: C - Last furnishing of labour or material, or completion as the statute defines it

Because Statutes run the clock from the claimant's last day of work or delivery, or from completion, cessation or a recorded notice of completion. Returning to do warranty or punch work generally does not restart it, which is a trap for the unwary. NASCLA Guide ch. 8

Where the other options lead

  • A.Uses the invoice. Payment terms are a contract matter and do not set the statutory clock.
  • B.Uses occupancy. Occupancy may evidence completion in some states and is not itself the trigger.
  • D.Uses the contract date. The right arises from the work, so the clock runs from the work.